Frequently Asked Questions

What is currently happening on site?

Storm water works

Installing storm water drainage along Brightwell Road, which will have an impact on East Street with a lane closure over the next few weeks.

Following the completion of the storm water drainage diversion the existing bus layby on East Street will be closed. This means that buses will continue to run as normal, but will be required to stop in the road until access is restored. This will allow the build to progress in this area in a safe manner for our construction team and members of the public.

Marlborough Head Pub

Works are progressing to restore the Marlborough Head Pub. Hoarding and scaffolding will be erected to allow for works to progress. The scaffolding will encroach along East Street, creating a gantry to walk under for pedestrian access and lighting installed along the hoarding.

Utility works

Over the coming weeks, works will continue on the foul sewer diversion, running through the site.

Site compound

Once the above utility works are complete, Crest will be erecting their main site compound. This will house Crest site office, canteen and meeting rooms.

Sheet piling works

To create the building foundations sheet piles need to be installed into the ground. Whilst the machine used for this is quiet, some vibrations can be felt whilst these works take place. The next piling works continue, week commencing 17th June. Please rest assured that Crest have monitoring stations in three locations around site, to monitor noise and vibration levels. These reports are shared with Waverley Borough Council and reviewed with Environmental Health on a monthly basis.

When will cranes be going up on site?

Cranes are needed in order to construct the buildings at Brightwells Yard. These will begin to be erected in June.

What impact will the development have on parking in Farnham?

Dogflud Car Park and the Green Parking area have been closed to enable works, and Waverley Borough Council have extended parking at Riverside 2 and 3 (Mike Hawthorn Way, GU9 7UQ) 395 spaces.

South Street Car Park has also benefited from five new disabled parking spaces.

When complete, the Brightwells development will provide a new multi-storey car park and over 400 new car parking spaces.

For full, current information on the car parks in Farnham, visit: www.waverley.gov.uk

What impact will the development have on traffic in Farnham?

Brightwells Yard includes an element of highways works, which have been agreed with Surrey County Council as the highway authority, in order to minimise congestion at the end of the scheme.

  • Work begins in autumn 2019 to part-pedestrianise East Street, traffic will be diverted to the Woolmead loop road which will become two-way
  • Improvement works begin on Brightwells Road and the South Street junction during spring 2020

Why has the bridge been built?

The temporary bridge allows construction traffic to enter the site without travelling through Farnham Town Centre. The bridge will reduce disruption from construction traffic during the works, preventing additional increases to traffic in the Town Centre.

Which retailers are signed up?

Current retailers legally committed to Brightwells Yard are Marks & Spencer Simply Food, Ask, Seasalt and Reel Cinemas. Given the early phase of the development, this is an ordinary level of lettings, and Crest Nicholson will be using the successful marketing strategy they have used on commercial aspects of many developments elsewhere to fill the units over time.

What are the Section 106 contributions for the development?

A Section 106 is a legal agreement between the developer and the planning authority, which is Waverley Borough Council. The purpose of a section 106 is to mitigate the impact of a new development on the existing community. Crest Nicholson have contributed in excess of £3 million towards infrastructure and community assets.

  • £100,000 towards traffic reduction in the town centre
  • £275,000 for the County Council’s park and stride scheme
  • £47,000 for travel vouchers or cycle provision
  • £64,000 for the provision of CCTV Security
  • £100,000 for the provision of new public art
  • £322,000 towards new sport and leisure experiences
  • £751,000 to fund the delivery of education in Farnham
  • £35,000 to support the future of library provision in Farnham creation of over 800 new jobs
  • £474,000 to enhance the green space and open up the natural environment
  • £800,000 towards the refurbished Memorial Hall the restoration of the Grade II listed Brightwells House

When will Brightwells Yard be completed?

The scheme will be completed in 2022, however, it is a phased opening with some completions as early as spring 2021.

  • The retail centre, including Marks and Spencer Simply Food, and town square opening will take place from spring 2021
  • Reel cinema will be finished in summer 2021
  • Between the spring of 2021 and spring of 2022, the residential units will be complete

Please see the development timeline for further information.

Is there an impact on local businesses?

Brightwells Yard should not impact on Farnham Town Centre. Businesses in the surrounding areas, such as those on Cambridge Place, East Street and the leisure centre, remain open for business throughout construction of Brightwells Yard. For information about car parking when visiting Farnham, please see the relevant FAQ.

Does Brightwells Yard include the Woolmead?

Brightwells Yard is being developed by Crest Nicholson and is separate to the nearby Woolmead development, which is led by Berkeley Homes. Brightwells Yard includes the area south of East Street, please see the masterplan for further information. If you would like to access the relevant planning applications for either scheme, please visit www.waverley.gov.uk

Is there any affordable housing at Brightwells Yard?

The delivery of 72 shared ownership affordable homes means that 30 percent of the homes in this new development will be affordable housing. Shared ownership will provide first time buyers with the opportunity to buy locally while the remaining homes will be delivered by Crest Nicholson for open market sale. The affordable homes will be delivered by Crest Nicholson for Thames Valley Housing Association.

Share us on

Sign up to our Alerts

  • This field is for validation purposes and should be left unchanged.

We use cookies to give you the best online experience. By agreeing you accept the use of cookies in accordance with our cookie policy.